- Principal YAYASAN PURNA BHAKTI PERTIWI
Name of Project LAND TRANSPORTATION OF KRI “HARIMAU” FROM ON WATERS TG.PRIOK PORT ONTO FOUNDATION AT TAMAN MINI INDONESIA INDAH
Material 1 COMPLETE BATTLESHIP
High Point LAND TRANSPORT OF A 20M LONG; 5.50M HIGH SHIP HULL
Execution 1990
- Principal PERUM LISTRIK NEGARA (PLN)
Name of Project SCATTERED DIESELS
Material 11 SETS G.E.C. DIESEL ENGINES FOR POWER STATIONS IN SENAYAN, KETAPANG & SUNGAI PENUH
High Point REMOTE UNFRIENDLY SITES
Execution 1990 through 1991
- Principal HYUNDAI ENGINEERING & CONSTRUCTION CO. LTD., SEOUL
Name of Project SEMEN CIBINONG EXTENSION PHASE III
Material CEMENT PLANT EQUIPMENT & MACHINERY
High Point SPECIFIC TRANSPORTS LOGISTICS SYSTEM, KILN WEIGHING 160T
Execution 1990 through 1991
- Principal PT. CITRA AMBENGAN INTERNATIONAL, JAKARTA
Name of Project TWO PIECES ALUMINIUM CAN INDUSTRY
Material MACHINERY FOR ALUMINIUM CAN PRODUCTION
High Point SPECIFIC TRANSPORTS LOGISTICS SYSTEM. DOOR TO DOOR
Execution 1990
- Principal PT. ONWARD PAPER UTAMA, JAKARTA
Name of Project SCOTT TISSUE PAPER MANUFACTURE
Material MANUFACTURING MACHINES & EQUIPMENT
High Point YANKEE DRIER OF 120 T
Execution 1990
- Principal HYUNDAI ENGINEERING & CONSTRUCTION CO. LTD., SEOUL
Name of Project COAL TERMINAL CONSTRUCTION IN EAST KALIMANTAN
Material CONSTRUCTION EQUIPMENT
High Point SPECIFIC TRANSPORTS LOGISTICS SYSTEM. REMOTE AREA UNFRIENDLY ENVIRONMENT, HEAVY PIECES UP TO 100T
Execution 1990 through 1991
- Principal PERUM LISTRIK NEGARA (PLN)
Name of Project RELOCATION GAS TURBINE POWER STATION FROM UJUNG PANDANG TO TARAHAN
Material 1 COMPLETE SET ALSTHOM GAS TURBINE
High Point GAS TURBINE WEIGHING 120T
Execution 1991
- Principal PT. KOMPAS INDONESIA, JAKARTA
Name of Project “INDONESIAN PRODUCT EXHIBITION 1991” IN SINGAPORE
Material EXHIBITION GOODS
High Point PRECISION TRANSPORTS LOGISTICS SYSTEM
Execution 1991
- Principal PT. INTI KARYA PERSADA TEHNIK, JAKARTA
Name of Project PETROKIMIA GRESIK
Material AMMONIA & UREA PLANT EQUIPMENT
High Point PRECISION TRANSPORTS LOGISTICS SYSTEM
Execution 1991
- Principal PT. PAL, SURABAYA / PT. HANDFAST FORWARDING
Name of Project 30.000 T SHIPYARD FACILITY
Material GENTRY CRANE FROM GOTTWALD
High Point 1 HEAVY PIECE OF 120 T
Execution 1991
- Principal PT. PAL, SURABAYA / PT. HANDFAST FORWARDING
Name of Project HYDRODINAMIC LABORATORY SUKOLILO
Material LABORATORY EQUIPMENT
High Point LANDTRANSPORT OF HEAVY & OVER SIZE PIECES
Execution 1991
- Principal PT. SEMEN GRESIK (PERSERO), GRESIK
Name of Project CEMENT TUBAN
Material COMPLETE SET EQUIPMENT & MACHINERY FOR NEW CEMENT PLANT IN TUBAN
High Point PRECISION TRANSPORTS LOGISTICS SYSTEM
Execution 1992 through 1993
- Principal DAVY BRITISH RAILWAY INTERNATIONAL, LONDON
Name of Project CIGADING – SERPONG RAILWAY REHABILITATION
Material RAILWAY EQUIPMENTS
High Point PRECISION TRANSPORTS LOGISTICS SYSTEM
Execution 1992 through 1993
- Principal PT. KAWASAN INDUSTRI JABABEKA, CIKARANG
Name of Project PRIVATE DIESEL POWER STATION
Material 11 UNITS DIESEL ENGINES
High Point HEAVY PIECES OF 55 T
Execution 1992
- Principal HYUNDAI ENGINEERING & CONSTRUCTION CO. LTD., SEOUL
Name of Project PAITON STEAM POWER STATION ELECTRICAL LOT FC-07
Material ELECTRICAL & MECHANICAL EQUIPMENTS
High Point SPECIFIC TRANSPORT & CUSTOMS CLEARING LOGISTICS SYSTEM
Execution 1992 through 1993
- Principal HYUNDAI ENGINEERING & CONSTRUCTION CO. LTD., SEOUL
Name of Project PAITON STEAM POWER STATION ELECTRICAL LOT FC-07
Material ELECTRICAL & MECHANICAL EQUIPMENTS
High Point SPECIFIC TRANSPORT & CUSTOMS CLEARING LOGISTICS SYSTEM
Execution 1992 through 1993
- Principal PERTAMINA – ATLANTIC RICHFIELD INDONESIA INC.
Name of Project OFF-SHORE NORTH WEST JAVA GAS DEVELOPMENT PROJECT BEACH PIPELINE APPROACH AND CABLE CROSSING
Material DIRECTIONAL DRILLING UNIT C/W ACCESSORIES
High Point SPECIFIC TRANSPORTS LOGISTIC SYSTEM
Execution 1992 through 1993
- Principal PT. FOOD SPECIALTIES INDONESIA (NESTLE), JAKARTA
Name of Project PT. NESTLE ASEAN INDONESIA NEW PRODUCTION UNIT IN KEJAYAN, EAST JAVA
Material COMPLETE SET OF MANUFACTURING EQUIPMENTS
High Point PRECISION TRANSPORTS LOGISTICS SYSTEM
Execution 1992 through 1993
- Principal PT. BOMA BISMA INDRA, PASURUAN
Name of Project PAITON STEAM POWER PLANT STATION
Material 4 UNITS HAMON SOBELCO CONDENSORS EACH WEIGHING 120 T; 24 M LONG
High Point HIGH PRECISION TRANSPORTATION TOOLS & METHOD TO AVOID FLEXIONS
Execution 1993
- Principal PT. BOMA BISMA INDRA, PASURUAN
Name of Project PAITON STEAM POWER PLANT PROJECT
Material 2 UNITS CONDENSOR TUBE BUNDLES FROM PASURUAN TO PLN’S OMBILIN SITE HEAVY EQUIPMENT IMPORT WITH 230B F ACILITY, SINGAPOREPROBOLINGGO-PASURUAN-PAITON
High Point HIGH PRECISION TRANSPORTATION TOOLS & METHOD TO AVOID FLEXIONS
Execution 1993
- Principal PT. SEMEN TUBAN, TUBAN
Name of Project ABB SUPPLY PACKET F FOR CEMENT TUBAN PROJECT
Material SPARE PARTS FROM SWEDEN, TURKEY, GERMANY
High Point HIGH LOGISTICS
Execution 1993 through 1994
- Principal PT. SEMEN CIBINONG, CIBINONG
Name of Project RE-EXPORT & RE-IMPORT FOR REFURBISHMENT FROM PT. SEMEN CIBINONG TO FULLER / USA
Material 1 ROLLER + 1 BEARING TOTAL 38
Execution 1993 through 1994
- Principal PT. NESTLE ASEAN INDONESIA, JAKARTA
Name of Project ERECTION MACHINERY FOR KEJAYAN PROJECT, PASURUAN
Material GENSET & BOILER
High Point SLIDING EXTRA LONG CONDENSER INTO COMPLETED BUILDING
Execution 1993
- Principal DAVY BRITISH RAILWAY INTERNATIONAL, JAKARTA
Name of Project CIGADING-SERPONG RAIL WAY INTERNATIONAL PROJECT
Material SIGNALLING EQUIPMENTS
High Point PRECISION TRANSPORTS LOGISTICS SYSTEM
Execution 1993
- Principal TASAN MEGAH JOINT OPERATION, CILEGON
Name of Project GUNUNG DRAJAT GEOTHERMAL POWER PLANT PROJECT
Material COOLING TOWER & EQUIPMENTS
High Point DIFFICULT MOUNTAIN ROAD ACCESS
Execution 1994
- Principal WSI CONSORTIUM, JAKARTA (WESTINGHOUSE, SAMSUNG, ITOCHU)
Name of Project BALI GAS TURBINE POWER PLANT PROJECT
Material POWER PLANT EQUIPMENTS HEAVY JETTY REINFORCEMENT TO ACCOMODATE ON DISCHARGING OF TURBINES
Execution 1993 through 1994
- Principal PT. INTI KARYA PERSADA TEHNIK, JAKARTA
Name of Project ARUN MOBILE OIL, SURABAYA – LHOKSEUMAWE
Material 36 UNITS BOOSTER
Execution 1994
- Principal GEC-ALSTHOM STAFFORD – U.K.
Name of Project OMBILIN STEAM POWER PLANT
Material ALL IMPORT CARGO AND LOCAL FABRICATION (45.000FT)
Execution 1994 THROUGH 1996
- Principal I K P T
Name of Project TRAIN G BONTANG
Material TRANSPORTATION LOCAL FABRICATOR EX SURABAYA & BATAM TO BONTANG (15.000 FT)
Execution 1996
- Principal THYSSEN HANIEL LOGISTIC SINGAPORE
Name of Project BILFINGER + BERGER MEKAR PUTIH SOUTH KALIMANTAN
Material PULAU LAUT BACK LOADING FACILITIES (5.000 FT)
Execution 1996 through 1997
- Principal THYSSEN HANIEL LOGISTIC SINGAPORE
Name of Project INCO EXPENSION PROJECT MALILI (150.000 ft)
Material HANDLING IN MALILI, SURABAYA, JAKARTA.
Execution 1996 through 1998
- Principal BOMA BISMA INDRA PASURUAN
Name of Project GUNUNG SALAK GEOTHERMAL POWER PLANT (FLUOR DANIEL / IKPT)
Material INLAND TRANSPORT 10 DEREATOR BBI PASURUAN TO GN. SALAK SITE
Execution 1996
- Principal BALCKEDURR INDONESIAName of Project MUARA TAWAR STEAM POWER STATION
Material 7 UNIT OVERSIZE CARGO EX. PUSPETINDO GRESIK
Execution 1996
- Principal AGUMAR
Name of Project METAEPSI TRANSMITION PROJECT
Material 5 UNIT TRANSFORMER 110 TON & ACCESS FOR JAKARTA
Execution 1996
- Principal BILFINGER + BERGER
Name of Project JAKARTA OUTER RING ROAD
Material PRESS STRESS BEAM
Execution 1997 – 1999
- Principal MAXUS / KWARTADAYA DIRGA NUSA
Name of Project MAXUS POWER PLANT
Material 2 UNIT COMPLETE SET TURBINE + GENERATOR & ACCESSORIES, FOR “SEA FOX” JACK-UP RIG
Execution 2000 – 2001
- Principal LEKOM MARAS
Name of Project EXPORT FISHING TOOLS TO THAILAND
Material COMPLETE SET OF FISHING TOOLS
Execution 2002
- Principal INDONESIA POWER
Name of Project COAL SUPPLY & TRANSPORTATION FOR PLTGU SURALAYA
Material 90.000 Mt of Coal
Execution 2002 – 2003
- Principal PERTAMINA – BALCKE DURR INDONESIA
Name of Project PERTAMINA BALIKPAPAN REFINERY
Material 2 UNIT BENFIELD SOLUTION STRIPPER (75 TONS WEIGHT, 50 LENGTH)
Execution 2003
- Principal PT. INDONESIA POWER
Name of Project COMBINE CYCLE POWER PLANT (CCPP) PROJECT PEMARON, BALI
Material COMPLETE SET MATERIAL & EQUIPMENT (6600 FT)
Execution June 2003 – May 2004
- Principal PT. PLN (PERSERO) PIKITRING KALIMANTAN
Name of Project TARAKAN POWER STATION
Material 2 UNIT COMPLETE SET DIESEL & GENERATOR
Execution August – October 2003
- Principal PT. TRIPATRA ENGINEERING – CONOCO PHILLIPS
Name of Project SOUTH JAMBI “B” SHALLOW GAS PROJECT
Material 2 UNITS COMPLETE SET GAS COMPRESSOR
Execution JANUARY – MARCH 2004
- Principal PT. TRIPATRA ENGINEERING – CONOCO PHILLIPS
Name of Project SOUTH JAMBI “B” SHALLOW GAS PROJECT
Material 2 UNITS COMPLETE SET GAS COMPRESSOR
Execution NOVEMBER 2003 – MARCH 2004
- Principal PT.CHIYODA INTERNATIONAL – PT.SEMPEC INDONESIA
Name of Project BETARA COMPLEX DEVELOPMENT (BCD)
Material 1 X 180FT- AIR COLLER AND HEAT EXCHANGER
Execution MAY 2004
- Principal PT.HICKHAM INDONESIA – SULZER
Name of Project PAITON POWER PLANT PHASE 3
Material 2 UNITS CYLINDERS PUMP
Execution MAY 2004
- Principal IKPT/CHIYODA
Name of Project BETHARA COMPLEX DEVELOPMENT (BCD PROJECTS)
Material INLAND TRANSPORT & SEA TRANSPORT ALL MATERIAL & EQUIPMENT EX. LOCAL FABRICATION
Execution JUNE 2004 – NOVEMBER 2004
- Principal ABB
Name of Project ANTAM Pomala
Scope:
- Transportation 1 unit transformer 80 Ton from Italy to Pomala
- Replace old transformer at 7 meter height with new one
Execution 2006
- Principal Texmaco
Scope : Relocation Tanjung Priok to Marunda Shore Base: 9 units Steel Mills Equipme t 120 Ton to 240 Ton
Execution 2006
- Principal PT Cikarang Listindo
Scope : Transportation and handling of 1 unit Turbine – 220 Ton + 1 unit Generator 160 Ton from Tg Priok to Cikarang via Citarum River
Execution 2007